Construction> A Case Study
A Good Old Fashioned Barn Raising (Part 1)
We had an opportunity to build a barn North of San Antonio, Texas.
This was not to be just any barn, but one 40 wide by 80 long with a
rear plate height of over 14 and a front height of 24. It would have
five garage doors: the smallest pair starting at 10 wide by 7 high to
the middle door being 12 wide by 14 high with arches over each one.
Add in 3 windows and one set of double entry doors and that pretty much
defined the structure to be built. Amazon Forms wanted to use the
opportunity to try some new installation techniques we had been
discussing as well as we were curious to find out just how good our
product is, and what improvements we could make to reduce the total cost
of a finished wall. Wanting to put ourselves in our customers shoes,
we formed a construction team consisting of Bill Bowers, Bill
Stipanovich, two production people from the factory (that we rotated in
and out over the days), and Randy Carroll-Bradd, the crew leader.
Because of the 24 finished height, we decided on doing two pours, one
at a height of 12 and one to finish the structure. We developed
checklists of materials, tools, and supplies as well as equipment we
thought would help us reduce the time and cost of the installation. All
personnel had virtually no experience installing Grid-Wall.
Before the Installation
The barn slab was engineered by a professional engineer and poured
with half-inch vertical rebar protruding from the slab approximately 32
in length on 16 centers to accept the Grid-Wall and Grid-Corner blocks
(see the block drawings under the Products section to get the exact
dimensions). You can tie in this rebar before the pour, insert your
rebar in the wet concrete, or come back later to drill and epoxy them in
place. We allowed the slab to sit and cure a little since we planned to
be working on the slab surface with material handling equipment.
|

Rebar being installed in slab as poured. |
|

The finished slab awaits our arrival. |
Day 1 Getting Started

Steel Garage Door Frame |
Day one consisted of moving the blocks from the drop point on the
road to the slab. We worked on the slab rather than in the dirt as the
terrain surrounding the slab was very rough and would require
all-terrain scissor lifts and forklift, significantly increasing the
cost of those rentals. Pallets of corner blocks were placed in the
corners where needed, and wall blocks were placed near their point of
use. The garage door frames had been previously assembled from 6
steel channel and the entry door and window buckings were constructed
from 2x10 lumber. Since the garage door
frames or buckings were made of steel, we welded rebar on the vertical
frame members spaced so as to tie in with the rebar between the courses
of block. These frames would be permanently attached to the building |

Double Entry Door Bucking |
|

Window Bucking |
|
Rings were cut from 2
diameter PVC approximately 2 long and slipped over the protruding rebar
from the slab. The rings will be used later to help keep the vertical
rebar centered when it is inserted prior to pouring the wall. |

PVC rings on slab rebar |
|

The first course is installed |
|
The first course or row of blocks is the most important to place. If it is not plumb or
vertical, then your wall will not be. We snapped a chalk line 10 in
from the outside edge of the slab to help us keep the wall straight. |

Measuring in 10 from edge of slab |
|

Snapping a Chalk line for the first course |
We started with placing the first course of all the corner
blocks and then used them to set up a string line to aid in placing the
wall blocks. We used bubble levels to check to insure that the blocks
were plumb to the slab and, if not, shimmed them until they were. Do not
drive the shims in but rather lift or tilt the block to accept the
shims. We also had drywall saws so we could level the block by sawing
the horizontal seam to remove material rather than shimming on the
opposite side. |

Setting a string line |
|

Leveling the first course with
shims |
|
Once we had the blocks plumb and in a straight line we spot
glued them in place so that they would not shift or move when the next
course was placed on top. We then moved on to placing the horizontal
rebar. |

Spot Glue the course to prevent shifting |
|

Tying the rebar with
overlap in corners |
|
We used either 40 penny nails or half inch rebar
cut into 8 pieces to serve as rebar supports (chairs), placing one in
the middle of every wall block and two at each corner block. When we
ordered the rebar, we had some cut and bent 90 degrees for use in the
corner blocks. We placed the sticks of rebar and the pre-bent corner
pieces on the rebar chairs overlapping the ends and wire tied them all
in place. We then repeated the process stacking, leveling, spot gluing
the blocks, and installing the rebar.
 40d nails used as rebar chairs
to support horizontal rebar placed on each course. When you add
another course the 4 bubble level comes in very handy. Use it to get
the course plumb but also use it to line the block being placed up with
the one below. It can also be used to make sure that the blocks continue
to be stacked in a straight line, though we found resetting your string
line for the next course worked best. The blocks may get damaged in
shipping or handling but are easy to repair. A corner may get broken off
but can be repaired quickly. If the broken piece is large and not lost,
just glue it back on. Otherwise, use the drywall saw to shape the hole
into a shape you can cut a plug for. Cut the plug from a piece of scrap
so that it fits snugly and glue it like you would when you stacked and
leveled. After the glue has set, check that the plug is tight by firmly
pressing against it it should not move or deflect. Gaps up to about 1
½ square can just be filled with glue. (picture of a plug) By the end
of day 1 we finished 3-4 courses around the perimeter which got us to a
height of 4 to 5-4. We did avoid the front of the structure where the
garage doors were as we needed 5-6 courses run before we could set the
door frames in place. Not bad, considering we did not place our first
block until around 10am! |

Day 1: Three to four courses high |
|

Door and window buckings in wall |
Day 2 Progress, Progress, progress
After about 5 courses, we brought in two rented scissor lifts to work
in conjunction with the rental forklift that we already had on site.
This was one of those things that we wanted to do differently than most
install crews do: At a normal plate height of 8-10 they might use
wheeled scaffolding to get around. There would be one to two workers on
that scaffold with one to two workers handing them blocks and
repositioning the scaffold as they went. If they used a scissor lift, it
would be lowered so a quantity of blocks could be loaded on the lift,
and then raised back up to the working level. Blocks would be placed,
and the lift lowered back to ground level for more blocks. Rarely would
there be a forklift on site other than to offload the pallets from the
delivery truck. We had a 5 person crew with 2 people in each electric
scissor lift and 1 gofer person on the slab driving the forklift and
supplying the scissor lifts with blocks, rebar, ties, etc. The forklift
was able to continuously position the
blocks at the height the people in
the scissor lifts needed to efficiently stack the blocks. One scissor
lift crew stacked blocks while another followed behind, leveling those
blocks and spot gluing them in place. The first lift crew then came
behind the second, placing rebar and tying it while the second lift made
another pass to place the next course of blocks. We moved people around
to cross-train and keep the progress moving forward. If we were running
behind in one part of the process we would get some help from a crew
that was running ahead. We kept repeating this process until we placed
the majority of the blocks. By the end of the second day we
had the majority of the building at 7 courses (9-4) with the exception
of the front of the building where we had just started to put the garage
door frames in place. The double entry doors bucking and the window
buckings were all surrounded by Grid-Wall at this time. This would be
normal plate height for most residences and the amount of block stacked
at this time would have been enough to complete a 2100 square foot
house. |

Day 1: Three to four courses high |
|

Door and window buckings in wall |
Continue On to Day 3
(Part 2) > > |