Construction> A Case Study
A Good Old Fashioned Barn Raising (Part 3)
Day 7 Arches are Completed
Fourteen courses are stacked at the front of the building allowing
all of the arches to be drawn, cut, and the press board inserted.
Blocks are stacked high enough to allow formation of all arches Day 8
Block Stacking is finished
The scissor lifts come in very handy when you are working 20’+ off of
the ground. The front of the building is completed to its finished
height. Diagonal rebar was inserted above the three middle arches to
provide additional roof supporting strength.
The side walls have the same slope as the roof.
The blocks are stacked, glued in place, and then a chalk line is snapped
for the cut line. An electric chain saw is used to make the cut.
The work crew also prepared for the
second pour doing those things listed in the first pour such as
inserting the vertical rebar and patching any voids in the block.
Day 9 - The Second Pour
Same preparation steps as the first one except with zero blowouts.
What we learned on our first pour regarding the arches paid off with no
leakage of wall-fill concrete during the second pour. The sloped side
walls were poured from the bottom to the top, with care being taken to
move up as cement appeared in the sliced horizontal tubes behind the
fill. We have more to show you rather than tell you.
Day 10 – Finishing the arches – And Done!
The second pour was on a Friday so we let the wall cure until the
following Tuesday before we started removing the arch support material
below the arches. We also did some rasping or smoothing on the inside
walls to remove any excess glue from our spot gluing process as well as
blend any blocks together that may have shifted during the stacking
process.

Remove the fully contained pieces |

Remove what ever possible by hand |

Cut away any excess with chainsaw |

Chip away small concrete deposits |
|
|
|