Day 4 – Working on the front, the arches
over the garage doors, and preparing to pour
We focused next on the front of the building and the arches over the
garage doors. This required the normal steps used to install Grid-Wall
plus setting the steel frames in place for the garage doors. The
forklift was handy for this job. Not a lot of block stacking was
required between the doors, but some time was spent securing the frames
and insuring that they were plumb to the slab. (arch pictures) We then
stacked the front 9 courses high to match the rest of the building.
Since they get removed after the pour, the blocks under the arches were
stacked loosely just to support the weight above, and were not glued
(note the double 2x4’s sitting in the door frame – used to support the
solid sections of these blocks). As soon as the blocks were high enough
to allow the whole arch to be drawn, an electric chain saw was used to
cut a slot 8” into the 10” thick blocks. A 10” wide strip of thin press
board, such as Masonite, was then inserted into the slot. During the
pour, the press board will stop the flow of concrete along the arch
line. After the pour, the support blocks are pushed out, the press board
is removed, and the last 2 inches of the slotted blocks are cut away,
forming the final shape of the arch.
20’ rebar was cut to extend 32”
beyond the 12’ stacked wall height. It was then inserted vertically
taking care to place the rebar inside the PVC rings that had been set
over the slab rebar on day 1. This helps keep the vertical rebar
centered in its column. The 32” extensions were to accommodate the
final 2 rows of blocks on the back wall, while the side and front
rebar were cut to extend approximately 40” allowing for the next 2
courses and 10 inches of rebar overlap with the next phase of stacked
blocks. Debris from sliding the blocks across each other during the
stacking and leveling process accumulates inside the wall at the slab.
It is important to wash this out so the concrete poured into the wall
can bond with the slab. Drain holes are cut from the blocks on the
bottom course to allow debris to be flushed out. Keep this cut out
piece from getting lost by screwing it with a deck screw to the wall
above the hole it came from. This will make it easier to plug the hole
again before the pour. Just insert the plug back into its hole and
spot glue it into place. (picture of drain holes). Day 5 – The first pour
Check out the specifics of what you need for the concrete. We started pouring under the
windows to insure that we had no entrapped air. We did this by cutting a
hole in the sill of the window buckings (best to do this before bucking
installation) and poured until we filled the blocks under the window.
Smaller window buckings do not require this whereas larger ones may
require one or more.
After we poured under the windows, we used the scissor lifts
in tandem and played a game of leap frog as we poured the walls. The
bracing on the slab cut up our nice 40’ and 80’ walls, forcing us to
frequently reposition the scissor lifts.
We did two passes or two laps pouring the 12’ high wall with
no blowouts except where our garage doorways met the arches. The
breaks were quickly repaired with some plywood and some deck screws,
and then we continued to pour that section. We had caused the blowouts
by positioning the block fragments with no material in place to hold
back the concrete. We corrected that on the next three arches and had
no issues. We had no blowouts at the holes we cut to flush debris from
inside the blocks, or on any other blocks, including those that had
been repaired.
We poured on a Tuesday and decided to allow the walls to set for a
few days and went back on Friday.
Day 6 – Arches, Arches, and more Arches
Two courses were added to the back and the two sides bringing the
back to the finished height.
Time was also spent on the front of the building covering the next two arches
in Grid-Wall. When working at this height and with arches, the installation rate
does slow down. |